BBS construction header image

Walthamstow Hall, Sevenoaks

Commencing works on site in July 2016, BBS are undertaking the construction of a new science block and 6th Form Centre at Walthamstow Hall School in Sevenoaks, Kent.

With completion due in Summer 2017, and at a value of almost £4million, the project comprises a reinforced concrete basement and frame, with steel frame structure, rain screen cladding and roofing systems.

The new building, attached to the existing science block, will house a  new 6th form centre, including study areas and break out space in the lower ground floor area, as well as new science laboratories and preparation areas, a computer room/study area, and technologies classroom spaces on the ground and upper floors.

As can be seen from the photograph, the concrete base structure is complete, and cladding works have begun, with the steel frame section due to be in place within the next few weeks.

IMG_8575