BBS construction header image

Case Study:

Contemporary private house at Leigh near Tonbridge

 

This six bedroom New Build house was built in extensive grounds with a high standard of finishes. The building consisted of a waterproof concrete basement and extensive remodelling of the external landscape and installation of a swimming pool.

MKA Architects were the designers on this project

 


Case Study:

Lynwood private house, Tunbridge Wells

New-House

 

 

This New Build project, designed by MKA Architects, was an individually designed house featuring many unusual architectural details.

This prestigious project won several design awards including the RIBA Downland Prize, The Kent Design Award Best Residential Scheme, Kent Design Award Overall Winner and was short listed for the National RIBA Awards.


Case Study:

MacDonald Court, Paddock Wood

McDonald-Court-1170x500

 

Completion in March 2015. £3.9m contractors D&B project. New build three storey block providing 39 affordable sheltered flats for Town & Country Housing Association. A Chartway development for our parent group company.

Logistically challenging site with limited access through a busy residential estate requiring close neighbourhood liaison with local residents and businesses during construction. Timber framed construction with brickwork, render and tile hung external features. Designed by BDB Design LLP of Canterbury.


Case Study:

Flats at Victory House, Church Street, Tovil

BBS_Church_Rd_Tovil01_lr

 

This project was carried out for a private developer and comprised of a three storey block of six flats and one new adjacent house. The contract value was £700k and it was completed in August 2014

A challenging foundation design to overcome the close proximity of adjacent properties and existing cellars, which formed part of the old pub previously on the site. the building was traditionally constructed with particular emphasis on sustainability including the use of photo voltaic panels on the pitch roof.

Designed by HMY Architects.


Case Study:

Heads House, Brambletye School, East Grinstead

Heads House & Garden Brambletye

Completed in September 2014 at this independent school in East Grinstead.

The New Headmaster’s House. Traditionally procured £400k project. New four bedroomed detached property with piled foundations. Timber framed construction with high standard of finishes throughout. Externally finished with render and chestnut cladding. Designed by HMY Architects.

This was the most recent phase of several BBS Construction carried out at this independent school including previously a new £1.2m teaching block on the main entrance drive into the School. Owing to its prominence, it was required to be both striking and in keeping with the old manor house which sits behind.

BBS & HMY Architects are currently helping the school cost future feasibilities here.


Case Study:

Cudham Frith Farm, Cudham

Cudham Frith Farm 1170x500

 

This New Build contract at Cudham Frith Farm, Cudham, comprised of the construction of a large three story individual house for a private client. All completed to a high standard of finish